POSTED ON BEHALF OF OXFORDSHIRE COUNTY COUNCIL:
Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure – at Witney, B4022 entry and exit slip roads to and from A40
In the interests of public safety it will be necessary for Oxfordshire County Council to close a short section of the A40/B4022 slip roads to facilitate works for drainage and services.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closures and will operate between 7 July 2025 and 22 May 2026, night time closures 20:00 to 06:00 hours . Dates for the closure are as follows:
Date | Number of shifts | Works description | Roads closed |
07/07/2025 | 5 Nights | Drainage S23 to S24, Area 2A DNO crossing | B4022, Onslip and Offslip closed |
01/09/2025 | 3 Nights | S3 to S9 Drainage | Offslip and B4022 closed |
01/10/2025 | 5 Nights | Street Lighting Crossings Area 2 | Offslip and B4022 closed |
22/10/2025 | 4 Nights | Traffic Signal Crossings Area 2 | Offslip and B4022 closed |
19/11/2025 | 5 Nights | Drainage and lighting crossings Area 3 | Offslip and B4022 closed |
01/12/2025 | 1 Night | Area 3B road crossing for illuminated sign | Onslip closed |
11/12/2025 | 2 Night | Area 3 traffic signal crossings | Offslip and B4022 closed |
06/02/2026 | 4 nights | Area 4 street lighting crossings | Offslip and B4022 closed |
02/04/2026 | 1 Night | Area 5 Street lighting road crossing | Offslip and B4022 closed |
13/04/2026 | 4 Nights | Area 5 Crossings for columns | Offslip and B4022 closed |
08/05/2026 | 10 Nights | Resurfacing B4022 | B4022, Onslip and Offslip closed |
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)
Access will be maintained for emergency service vehicles and for those frontages within the closure area, subject to the progress of the works and liaison with the works supervisor.
A copy of the drawing showing the extent of the closure and the alternative routes for traffic is attached.
Further information regarding the works may be obtained by contacting Nicholas Evans-Milestone Infrastructure – Oxfordshire County Council on 0345 310 11 11.Or email nicholas.evans@milestoneinfra.co.uk